200kW, 500kW or 1MW Solar: How Should a Business Size Commercial Solar?
A roof that can fit 500 kW of solar does not automatically need a 500 kW solar system.
And a business using a large amount of electricity each year does not automatically need a large solar array.
For commercial solar, when electricity is consumed can be just as important as how much electricity is consumed.
That is why proper system sizing should begin with the site’s electricity data, operating profile and commercial objectives rather than a product catalogue or arbitrary capacity target.
The Government’s announced expansion of the SRES above 100 kW also makes this more relevant. Our guide to commercial solar over 100 kW explains what the announced STC changes could mean for projects between 100 kW and 1 MW.
If eligible systems above 100 kW and up to 1 MW can access STCs as intended, businesses may have less reason to design around the historical 100 kW incentive boundary.
How much solar can the business actually use effectively?
| Factor | Why it matters for commercial solar sizing |
|---|---|
| Interval electricity data | Shows when the site actually uses electricity throughout the day |
| Daytime load | Helps determine how much solar can be consumed directly onsite |
| Solar self-consumption | Higher onsite use can improve the value of solar compared with exporting |
| Maximum demand | Shows whether solar generation overlaps with periods of high grid demand |
| Network export limits | May restrict how much excess solar can be exported to the grid |
| Roof or ground space | Sets a physical limit, but should not determine system size on its own |
| Future electricity demand | Allows for business growth, new equipment and electrification |
| Battery integration | Can increase how much daytime solar is stored for later use |
Why annual electricity consumption is not enough
Suppose two businesses each consume 1,000 MWh of electricity per year.
On paper, their annual consumption is identical.
But imagine their operating profiles are completely different.
Business A
- manufacturing operates from 7 am to 5 pm
- machinery runs throughout the day
- electricity demand remains high during solar-production hours.
Business B
- relatively low daytime demand
- refrigeration and production loads rise late in the afternoon
- substantial electricity use continues overnight.
Both sites use the same amount of electricity annually.
But Business A may be able to self-consume substantially more daytime solar.
Business B may require a smaller solar array, battery storage or a different system design.
That difference is difficult to see from annual kWh alone.
Start with interval electricity data
Interval meter data shows when electricity is being consumed throughout the day.
Depending on the meter, readings may be available in intervals such as 5, 15 or 30 minutes.
This allows a commercial solar assessment to identify:
- morning load
- midday load
- afternoon load
- overnight base load
- maximum demand
- weekday versus weekend patterns
- seasonal changes.
Instead of estimating from a bill total, the solar model can be compared against the site’s actual consumption profile.
Carbon Heroes designs commercial solar systems around the site’s actual electricity profile rather than selecting capacity from roof space alone.
Daytime demand is critical
Commercial solar generally creates the strongest opportunity when a business uses electricity at the same time the solar system is producing it.
Consider a site that regularly has a 300 kW daytime load.
A larger solar array may be able to supply a significant portion of that demand directly behind the meter.
Compare that with a site whose midday load often falls below 50 kW.
Once solar generation exceeds onsite consumption, the additional electricity must either:
- be exported
- charge a battery
- be curtailed.
That does not automatically make additional solar uneconomic, but it changes the calculation.
Understand solar self-consumption
Solar self-consumption is the proportion of generated solar electricity used directly by the site rather than exported.
For commercial projects, this can be a particularly important metric.
Electricity consumed behind the meter avoids purchasing that electricity from the grid.
Exported electricity, by contrast, may receive a different financial value.
The optimal system therefore depends not only on annual solar production but on how much of that generation overlaps with the site’s electricity demand.
A useful commercial model should estimate:
- solar generated
- solar consumed onsite
- solar exported
- possible curtailment
- potential battery charging.
Don’t size the system to the roof alone
Roof capacity is important, but it should generally be treated as a constraint rather than the main sizing calculation.
A commercial roof assessment may need to consider:
- available usable area
- structural capacity
- roof condition
- orientation
- shading
- existing HVAC or mechanical plant
- skylights
- fire-access requirements
- maintenance access.
There is little value in simply maximising panel count if a large proportion of generation has limited commercial use.
On the other hand, a business expecting significant future electricity growth may deliberately allow for a larger array.
Maximum demand also matters
Many commercial electricity tariffs include demand charges.
These can be based on the site’s maximum demand during defined billing or tariff periods.
Solar may reduce grid demand when high site loads occur during daylight hours.
But solar will have limited impact on a demand peak that repeatedly occurs after sunset.
That is why reviewing when maximum demand occurs can be more useful than looking at the maximum-demand figure alone.
It can also help determine whether battery storage deserves further assessment.
Network export limits can change the design
A commercial solar project also needs to work within the site’s network connection.
The electricity distributor may impose limits on how much power can be exported.
This does not always mean the solar array itself must be the same size as the export limit.
Depending on the project and network approval, export-control systems may allow a larger solar installation while limiting the amount sent to the grid.
For example, a business with substantial daytime demand may consume most solar production onsite while limiting exports when site load falls.
This requires proper engineering and network approval.
It should be assessed early rather than discovered after the solar design is complete.
Think about future electricity demand
A commercial solar system may operate for decades.
Sizing purely around today’s electricity bill can therefore be short-sighted if the business expects material changes.
Potential future loads include:
- additional production machinery
- larger refrigeration systems
- warehouse expansion
- new tenants
- longer operating hours
- electric process heating
- EV chargers
- fleet electrification
- additional air conditioning.
A business planning to electrify a vehicle fleet, for example, may have a very different daytime electricity profile in three years.
The solar assessment should therefore consider both the current load and credible future loads.
How does battery storage change commercial solar sizing?
Commercial battery storage can change the point at which additional solar becomes useful.
Instead of exporting all excess daytime generation, some of that electricity may be stored and used later.
Depending on the site, a commercial battery may support objectives such as:
- increasing solar self-consumption
- shifting electricity use to different times
- managing selected demand peaks
- supporting critical loads during an outage, where properly designed
- responding to network constraints.
However, adding a battery does not automatically justify oversizing solar.
The battery also needs to be modelled against:
- available solar surplus
- charge and discharge windows
- usable capacity
- site demand
- tariff structure
- commercial objectives.
For NSW businesses, it may also be worth understanding the separate BESS4 and BESS5 commercial battery incentive pathways.
200 kW, 500 kW or 1 MW: which is right?
There is no universal answer.
| Example system size | May suit a site where | Key things to assess |
|---|---|---|
| Around 200 kW | Daytime demand consistently supports more than a traditional 100 kW system | Self-consumption, roof space, export limits and daytime load |
| Around 500 kW | The facility has substantial and relatively consistent daytime electricity demand | Interval data, network capacity, exports, maximum demand and future growth |
| Around 1 MW | A large facility has high electricity demand and substantial suitable roof or ground space | Network approval, engineering, self-consumption, project economics and future loads |
These are not fixed sizing rules. Two businesses with similar annual electricity consumption can require very different solar systems depending on when they use electricity, their network connection and their future energy requirements.
How does the announced SRES expansion change this?
Historically, commercial solar design sometimes had an additional question:
Should we stay at or below 100 kW because of STCs?
That threshold existed partly because projects above 100 kW generally moved into a different certificate framework. See our explanation of STCs vs LGCs for commercial solar.
The Australian Government has announced plans to extend the SRES to eligible solar PV systems above 100 kW and no more than 1 MW.
The intended commencement date is 1 October 2026, subject to regulations being in place.
If implemented as announced, the historical STC threshold should become less of a reason to artificially restrict a project to around 100 kW.
Another important part of the announcement is the proposed five-year mid-scale STC factor. See how the commercial solar STC deeming period is intended to work through 2030.
But the incentive should not become the new sizing method either.
A business should not install 1 MW simply because the scheme permits it.
The project should still be sized around electricity demand and commercial value.
Regulatory note
As at 9 September 2026, the mid-scale SRES expansion has been announced but has not yet commenced. The intended 1 October 2026 start remains subject to regulations being in place.
What data should you gather before asking for a commercial solar design?
Ideally:
- 12 months of electricity bills
- interval meter data
- current electricity tariff
- maximum-demand information
- site operating hours
- roof plans or suitable site information
- known future electricity loads
- details of existing solar or batteries
- any known network export restrictions.
From there, different system capacities can be modelled against the same site.
That gives the business a more meaningful comparison than simply quoting one predetermined solar package.
Don’t optimise only for payback period
Simple payback is useful, but it is not the only commercial objective.
Different businesses may prioritise:
- reducing annual electricity expenditure
- protecting against future electricity costs
- reducing peak demand
- reducing emissions
- making better use of roof space
- supporting electrification
- improving energy resilience.
The appropriate solar and battery design should reflect those priorities.
The takeaway
The best commercial solar system is not automatically:
- 99 kW
- the largest system the roof can fit
- the size receiving the greatest incentive.
It should be the system that best matches the site’s electricity profile, commercial objectives and technical constraints.
With the historical 100 kW STC barrier expected to become less important for eligible mid-scale solar, now is a good time for businesses considering larger systems to reassess what their site can actually support.
Export limits can force a smaller — or smarter — design
A site with room for 500 kW but a 200 kW export limit needs a different design conversation: higher self-consumption, curtailment settings, or battery storage to absorb midday surplus. See how batteries change the equation in how commercial batteries solve peak demand and grid constraints and what the combined incentive looks like in our NSW commercial battery rebate guide.
Where export is constrained, modelling 200 kW with high self-consumption against 500 kW with curtailment often shows the smaller system delivering better value per dollar — even before certificates are considered.
Planning a commercial solar project?
Carbon Heroes can review your interval electricity data, tariff, daytime load and site requirements to help determine an appropriate commercial solar and battery capacity.
The assessment can also consider whether a system above 100 kW makes sense rather than automatically designing around the historical STC threshold.
Learn more about our commercial solar assessment and design approach, or talk to us about your site for a site-specific sizing assessment.